How do you choose a software developer?

By David Kim, founder · Last updated 20 November 2026

Check they're a real business, and call two of their past clients. Get a written plan with dates and prices. Then pay in small stages, and see each stage working before you pay for the next. Software jobs go over budget often enough that these checks are worth it (Oxford study).

Why do software jobs go over budget?

Researchers at Oxford looked at 1,471 IT projects. On average, they cost 27 percent more than planned. One in six went much worse: about three times the planned cost, and almost 70 percent late.

Most of those were big projects, but small jobs go wrong for the same reasons. The plan is unclear, everything is built at once, or the job changes halfway.

Small stages keep the risk small. The UK government tells its own teams to start small, test and improve. Build it all in one go, and you get one chance to get it right.

How do you check a developer?

What should the written plan include?

A written plan for a software job is often called a scope. business.gov.au lists what a contract should cover. For software, it should say:

A one-page scope: what gets built, the price, the dates and who owns what.Example

What are the warning signs?

Is a one-person software firm risky?

It can be, so ask about it. Business Queensland says to ask any supplier what happens if they close down. With one person, getting sick or closing down hits harder.

These make the risk much smaller:

Big firms have this risk too, because one developer often does most of your job and can leave. With a small firm, you talk to the person who builds it.

How long does it take?

It depends on the size. QSM, a company that sells planning tools for software projects, studied thousands of them. A typical one took about five months with five people. The smallest took a bit over three months. A link between two systems can take a few weeks.

However long it takes, you should see something working every two weeks or so.

How much of your time will it take?

About an hour or two a week, answering questions and checking each stage. Choose one person who knows the job well, and let them make the calls. Projects get stuck when nobody on your side can decide.

What should you ask on the first call?

  1. Who will build it, and can we talk to them?
  2. Can we call two past clients?
  3. Is the price fixed? What does each stage cost?
  4. How often will we see it working?
  5. Who owns the code and the data? What does it cost to buy the code?
  6. What happens to our software if you close down?

What would we do?

Ask us all of these. MERIT is small, and David builds the software himself, so you talk to him from the first call. Every written quote has a fixed price, the price to buy the software, and stages you see working every two weeks. Your data is always yours.

Book a free 30-minute call.

We look at where your team's hours go and tell you the first thing worth building, whether you hire us or not.

More guides

Sources

  1. Bent Flyvbjerg and Alexander Budzier, Why Your IT Project May Be Riskier Than You Think, Harvard Business Review, 2011. 1,471 IT projects, mostly large.
  2. GOV.UK Service Manual, Agile delivery.
  3. Australian Business Register, ABN Lookup.
  4. business.gov.au, Suppliers.
  5. business.gov.au, Prepare a contract.
  6. Business Queensland, Finding and working with suppliers.
  7. GOV.UK Service Manual, Maintaining version control in coding.
  8. QSM, What does a typical software project look like? and Are your software projects too small? Research by a company that sells planning tools.

All sources checked 20 November 2026. This guide is general information, not legal or financial advice.